Year: 2024
Owner: Metro Vancouver
Location: Douglas Road Main #2
Installation of 1.1km of 1,524 mm line and coated steel water pipe, 2 air valve and blow down chambers, 2 cast in place valve chambers, full road reconstruction.
by Colleen Kott
Year: 2024
Owner: Metro Vancouver
Location: Douglas Road Main #2
Installation of 1.1km of 1,524 mm line and coated steel water pipe, 2 air valve and blow down chambers, 2 cast in place valve chambers, full road reconstruction.
by Colleen Kott
Year: 2022
Owner: City of Surrey
Location: King George Blvd and 69th Ave, as well as 135th Street and 69th Ave
Supply and upgrade approximately 1350mm of Concrete storm sewers, complete with Tee manholes and a 4200mm x 2400mm box chamber
by Colleen Kott
Year: 2020
Owner: Metro Vancouver
Location: Multiple streets within the City of Surrey
Supply and install 2.3 km of 1500mm steel pipe c/w 1 “pour-in-place” valve chamber, 1 blowdown and 4 air valves.
Work included augering of 36 metres of 1800mm steel casing pipe across 148th Street and 108th Avenue which housed 1500mm steel pipe.
The project was challenged by major road restrictions as well as extensive road rehabilitation.
by Colleen Kott
Year: 2020
Owner: City of Langley
Location: Langley Bypass & 56th Avenue
Removal of 3 1500mm CSP culvert pipes. Replace with 35 metres of twin 3m x 1.5m concrete box culverts c/w 4 end walls.
Reline existing 1200mm culvert pipe using 900mm Weholite pipe c/w headwalls.
Project required extensive bypassing of an environmentally sensitive creek system.